Excavator and loader productivity calculator

Earthmoving output comes down to three things: how much each bucket carries, how many cycles the machine completes in an hour, and how much of each hour is spent working. These calculators estimate hourly production of an excavator or wheel loader, the number of passes to fill a truck, and how many trucks keep the loading machine busy. They are planning estimates; site conditions, operator skill and material vary widely.

Hourly production

Multiplies bucket capacity by the fill factor and the number of cycles per hour, reduced by job efficiency — the share of each hour actually spent digging. A 50-minute working hour is the usual planning assumption.

Results
Effective cycles per hour—cycles/hCycles completed in a working hour.
Production—m³/h (loose)Loose volume moved per hour.
Production—t/hTonnes moved per hour.

Formula
cycles/h = 3,600 / cycle time × working minutes / 60
production = bucket × fill × cycles/h

Passes to fill a truck

Works out how many bucket loads fill a truck to its payload and how long loading takes. Three to five passes is a well-matched loader and truck; more than about six slows the whole operation.

Results
Tonnes per pass—tMaterial in each bucket load.
Passes needed—passesRounded up to whole bucket loads.
Loading time—sPasses multiplied by cycle time.

Formula
per pass = bucket × fill × density
passes = ⌈payload / per pass⌉

Trucks needed to keep the loader busy

A loader works continuously only if a truck is always waiting. The number of trucks needed is the full truck cycle — loading plus haul, dump and return — divided by the loading time.

Results
Trucks (exact)—trucksTheoretical number of trucks.
Trucks to use—trucksRounded up so the loader never waits.

Formula
trucks = (loading time + travel time) / loading time

Worked example: a 20-tonne excavator loading trucks

  1. A 1.2 m³ bucket at 90% fill on a 20 s cycle, working 50 minutes an hour, completes 150 cycles.
  2. Production: 1.2 × 0.9 × 150 = 162 m³ of loose material, about 259 t at 1.6 t/m³.
  3. Each pass carries 1.94 t of 1.8 t/m³ gravel, so a 25 t truck needs 13 passes — about 4.3 minutes.
  4. With an 18-minute haul, dump and return, six trucks keep the excavator loading continuously.

Typical bucket fill factors

MaterialFill factor
Moist loam, sandy clayabout 100 – 110%
Sand and gravelabout 95 – 110%
Hard, tough clayabout 80 – 90%
Well-blasted rockabout 60 – 75%
Poorly blasted rockabout 40 – 50%